Documented field work

Before, rebuild and recorded result

Closed white electrical panel and duplex receptacle installed on a dark blue wall above a wood-look floor.
afterCompleted installation of a wall-mounted electrical panel and receptacle.
Plug-in outlet tester displaying 120 VAC and “CORRECT” at a wall receptacle.
afterOutlet testing confirms 120 VAC and correct wiring.
Open residential electrical panel showing multiple installed circuit breakers and manufacturer safety labels.
detailCompleted electrical panel installation with multiple circuit breakers in place.
Electrical breaker panel with multiple installed circuit breakers and blank breaker spaces.
detailCompleted electrical panel installation with organized circuit breakers.
Open residential electrical panel showing installed circuit breakers, labeled circuits, and the panel door’s safety instructions.
detailCompleted electrical panel installation with labeled circuits and installed breakers.
Open residential electrical service panel showing multiple circuit breakers and connected red, black, and white wiring.
detailElectrical service panel with breakers and connected branch-circuit wiring.

The need

The recorded job scope was the installation of a new outlet. The evidence does not identify a broader electrical issue or provide details about the property beyond the municipality of New Westminster.

PTX's approach

The approved fixed-price scope included installation of the outlet and permit cost. The listed materials included a 1 Gang Easy Box galvanized steel device box, miscellaneous material and a 1P 15A combination arc-fault Homeline breaker. The permit setup was recorded under EL-2118267-2026.

The recorded result

The job record shows the approved scope as completed on September 3, 2026. It also records a requested final inspection. The evidence does not state that the inspection was completed or passed. The job file also records permit set-up EL-2118267-2026 and identifies the approved fixed-price scope as including permit cost, a one-gang galvanized steel Easy Box device box and miscellaneous material. Those items describe the documented scope only; they do not establish a broader diagnosis, a passed inspection or a performance claim.

What another customer can take from this example

This is one recorded example, not a diagnosis for another property. It shows why an outlet installation may be documented alongside the specific breaker, device box, permit cost and inspection step included in the job scope. A qualified assessment is needed to determine what another property requires.

Frequently asked questions

Questions property decision-makers ask

What was included in this New Westminster job?

The recorded scope included installation of a new outlet and permit cost. A 1P 15A combination arc-fault Homeline breaker and a 1 Gang Easy Box galvanized steel device box were also listed.

Was the final inspection completed?

The record states that a final inspection was requested. It does not confirm that the inspection was completed or passed.